Guides & news ·

Building in Asunción: 20% of the tax upfront, 30% fine without permit

Two-storey modern concrete house under construction, with large windows and a bare earth yard
Phichat Phruksarojanakun/Shutterstock.com

Before you build, extend or renovate in Asunción, the city must approve your plans and you pay the construction tax: 20% when you apply, the rest within 60 days of approval. Building without a permit costs the owner a fine of 30% of the unpaid tax and the builder 50%.

By

Share
  • LinkedIn
  • WhatsApp
  • Telegram
  • Facebook
  • X

Anyone who wants to build, extend or renovate a house or building in Asunción must first obtain the city's authorisation and pay the municipal construction tax: 20% of the estimated tax when the application is filed, and the balance within 60 days of written notice that it has been approved. Work may start only once the tax is paid in full. The rules are in Articles 32 to 43 of Law No. 881/1981 on Asunción's municipal taxes.

Key points:

  • Payment: 20% with the application, the balance within 60 days of approval; the permit to start comes after full payment (Article 36).
  • Building without a permit: a fine of 30% of the unpaid tax for the owner and 50% for the builder, plus the tax itself, and the work can be stopped (Article 43).
  • Exempt: single-family economy houses of up to 80 m² of covered area built without profit, which still need plans and a permit (Article 42).

1. What you file with the city

  • The application and the project: the owner files the building project with plans and cost sheets, naming the professional who signs them (Article 33).
  • The professional is the builder: the signatory is treated as the builder and is responsible until the final inspection, unless proven otherwise (Article 33).
  • The expected timeframe: the application must state the estimated time to finish the work (Article 33).
  • The city's decision identifies the property, the main features of the work, its use, the owner, the professional and the tax due (Article 33).

2. How the tax is worked out

  • Base: the value of the work in the cost sheet, which cannot be lower than the average unit prices the city sets each year by ordinance (Article 35).
  • Classification: works are classed by final use, type of construction, quality and materials (Article 34); the rate comes from the scale in Article 38 of the law, and extensions pay according to the same scale.
  • Demolition: a tax of 0.5% of the fiscal value of the building being demolished (Article 40).

3. Paying, withdrawing, starting again

  • Two instalments by law: 20% on application, the balance within 60 days of the approval notice (Article 36).
  • Withdrawn applications: the city keeps the advance if the owner withdraws; missing a second summons, not returning a file with objections within 90 days, or not paying the balance on time all count as withdrawal (Article 37).
  • Starting again within 24 months: if the project is resumed or adjusted and approved in that period, 65% of the advance already paid is credited (Article 37).
  • In practice in 2026: the city's private works department (Dirección de Obras Particulares) said on 10 August 2026 that the approval payment can be split, but the approval resolution and the stamped plans, which allow construction to start, are issued only after the last instalment is paid. New projects can be filed digitally through the city's SATI system. From 1 to 19 October 2026 the department closed 97 files, including 10 new building projects, 17 regularisations of plans and 62 final inspections (note of 21 October 2026).

4. Final inspection and changes

  • Who asks for it: the owner, the builder, or the city on its own initiative (Article 39).
  • Changes during the work: if the classification changed or the work was extended, the city re-assesses at current values and the owner pays the difference within 30 days of notice (Article 39).
  • Safety items: for a private home, the department lists smoke and heat detectors, fire extinguishers where required, and residual-current circuit breakers (disyuntores) among the basic requirements (note of 10 August 2026).

5. Exemptions and penalties

  • Economy single-family homes up to 80 m² built individually or collectively without profit, and primary school buildings of private schools, trade unions, political parties and religious bodies, are exempt (Article 42).
  • The exemption is not a free pass: plans and a permit application are still compulsory; whoever extends an exempt house within one year of the final inspection pays tax on the whole building, after that only on the extension (Article 42).
  • Without a permit: 30% of the unpaid tax for the owner, 50% for the builder; the work is suspended if tax and fine are not paid within 30 days of notice, or if it breaks the city's technical rules (Article 43).

The figures for a typical case, set out by us

Take a project whose construction tax, according to the scale and the cost sheet, comes to ₲20,000,000:

  • With the application: ₲4,000,000 (20%).
  • Within 60 days of approval: ₲16,000,000.
  • Withdrawn and resumed within 24 months: ₲2,600,000 of the advance is credited (65%); ₲1,400,000 is lost.
  • Built without a permit: the owner pays the ₲20,000,000 tax plus a ₲6,000,000 fine; the builder pays a ₲10,000,000 fine. Total ₲36,000,000, 80% more than the tax alone.

What it means if you build or buy in Asunción

  • Budget the tax before the first brick: 20% goes out with the application, and nothing may start until it is all paid.
  • Choose the signing professional carefully: they answer for the work until the final inspection.
  • Buying an existing house: ask for the approved plans and the final inspection; extensions that were never declared can be re-assessed at current values.
  • Small homes are not off the radar: even an exempt house needs plans and a permit.

The builder's liability once the work is finished is covered in the guide on building a home and the 10-year liability. Prime Properties presents its services for investors, and the Real Estate service of Partners.com S.A. assists with property purchases.

Sources

Ask the team

A few lines are enough. The team of Partners.com S.A. in Asunción reads every request and replies in your language.

We send a confirmation link to this address: your request reaches the team only after you confirm it.

Phone (optional)

Country code: type the number (with or without +) or the country name, then pick it from the list.

Digits only, without the country code.

At least 20 words: what you are looking for, budget range if relevant, and your timeline. No links, please.

Your request goes to Partners.com S.A., the company that provides the services of Prime Properties.

All guides and news