San Lorenzo stream: 850 m flood channel 64% built, due in July 2027

Calm canal lined by modern apartment buildings and greenery under a clear blue sky

The Ministry of Public Works is lining 850 metres of the San Lorenzo stream with a concrete channel to improve storm drainage and cut flood risk. Works were 64% complete on 12 November 2026 and are due to finish in July 2027, with a linear walk and two squares.

By

Share
  • LinkedIn
  • WhatsApp
  • Telegram
  • Facebook
  • X

Homes along the San Lorenzo stream, in the Central department, will get a concrete channel meant to drain storm water and reduce flooding: 850 metres of channel, 64% complete on 12 November 2026 and due to be finished in July 2027, according to the Ministry of Public Works and Communications (MOPC). The works come as the Directorate of Meteorology and Hydrology forecast, on 23 November, more rain with occasional thunderstorms for the coming days.

Key points:

  • 850 metres of concrete channel on the San Lorenzo stream, to improve storm drainage and reduce the risk of flooding.
  • 64% complete on 12 November 2026; completion planned for July 2027, which the contractor has undertaken to bring forward.
  • Along the channel: a linear walk with railings and solar-powered lighting, a new square and a renovated one, both with playgrounds and outdoor exercise equipment.

1. The works

  • Channel: 850 metres, built to improve storm drainage and reduce flood risk in the area.
  • Stage reached on 12 November: crews were assembling the channel's floor slab ahead of pouring 100 cubic metres of concrete planned for the next day.
  • Further stages: the minister said further stages will follow the first one.
  • Public space: a linear walk with railings and solar-powered lighting, a new square and the renovation of an existing one, with children's play areas and outdoor exercise equipment.
  • Supervision: the MOPC's coordination unit for drinking water, sanitation and hydraulic works (CAPSOH).

2. The timetable

Completion is planned for July 2027. The minister said the contractor has committed to finishing ahead of the contractual deadline; no new date has been published.

What is left, by our count

  • Share still to build: 36% of the works on 12 November 2026.
  • Time left to the planned finish: from mid-November 2026 to July 2027, between seven and eight months.
  • This rainy season: the channel will not be finished for the storms of November and December 2026; the benefit for drainage starts with the next season.

What it means if you own or buy near the stream

  • Check how close the property is to the stream and whether it lies on the stretch being channelled: the MOPC note does not publish a map.
  • Until July 2027 the area keeps its current drainage.
  • Afterwards: a channel, a lit linear walk and two squares change the setting of the homes that face them.

Other works in San Lorenzo are covered in the guide on Avelino Martínez avenue. Prime Properties presents its services for investors, and the Real Estate service of Partners.com S.A. assists with property purchases.

Sources

Ask the team

A few lines are enough. The team of Partners.com S.A. in Asunción reads every request and replies in your language.

We send a confirmation link to this address: your request reaches the team only after you confirm it.

Phone (optional)

Country code: type the number (with or without +) or the country name, then pick it from the list.

Digits only, without the country code.

At least 20 words: what you are looking for, budget range if relevant, and your timeline. No links, please.

Your request goes to Partners.com S.A., the company that provides the services of Prime Properties.

All guides and news