Two projects of the Ministry of Public Works are rebuilding route D025 in Luque: the widening of Tape Tuja avenue, 4.485 km due in 2027, and the third carriageway towards Mariano Roque Alonso and the airport, a PYG 208,817,595,138 contract. Both add service roads for access to the neighbourhoods and storm drainage.
By Emilio Marruso · Updated
Anyone looking at a home in Luque, the city between Asunción and the international airport, will find two building sites on the same departmental route, the D025. The Ministerio de Obras Públicas y Comunicaciones (MOPC) published the state of both in late October 2026. Here is what each one changes, in figures, and what to check before buying nearby.
1. Tape Tuja: the avenue to Asunción doubled
The first work is the duplication of the D025 on Avenida General Elizardo Aquino, known as Tape Tuja, part of the Las Residentas road corridor between Luque and Asunción. According to the MOPC note of 24 October:
- Length: 4.485 kilometres.
- Progress: the ministry expected 57% physical and financial progress by the end of October.
- Las Residentas interchange: 85% complete, with ramps built from stacked blocks and fill.
- Avay stream: a new four-lane bridge; the deck slab is finished in the Asunción–Luque direction, and the rectangular discharge channel is complete.
- Drainage: box culverts at 80%; the storm drainage is meant to reduce flooding in parts of Luque, Fernando de la Mora and areas linked to San Lorenzo.
- Service road: a collector road for residents to enter and leave the neighbourhoods and reach internal streets.
- Dates: parts open progressively as milestones are reached; full completion is planned for 2027.
2. The third carriageway towards Mariano Roque Alonso and the airport
The second work is the triplication of the D025 between Luque, Mariano Roque Alonso and Asunción, inspected by the minister on 27 October. The project extends the motorway and turns the existing road into a collector avenue, linking Luque, Mariano Roque Alonso and Limpio with the northern access to Asunción.
- Traffic split: a new carriageway for light vehicles and the existing one reinforced for heavy traffic.
- Airport: the collector road is extended to the access roundabout of Silvio Pettirossi International Airport.
- Link to route PY03: Avenida General Díaz is being paved, on a route that starts at the airport access and runs along General Bernardino Caballero street.
- Itay stream: a new 60-metre concrete bridge is finished; the old one will become part of the collector system.
- Drainage: culverts, gullies and storm channels, including on airport land.
- Contract: design and works by CDD Construcciones S.A. for PYG 208,817,595,138, financed by Itaipú Binacional through the Itaipú Technology Park Foundation, supervised by GEPG S.A. The note gives no completion date.
What it means if you are buying
- Check which side of the works the street is on. Both projects build collector roads to reach the neighbourhoods: ask whether the street of the home connects to one, and where.
- Drainage is part of the price of the area. Both works add storm drainage; ask whether the street flooded before and whether it falls in the area served.
- Building sites until 2027. Tape Tuja opens in stages; for the triplication no end date is published. Noise and detours are part of the short term.
- The airport is a factor. The triplication changes the route to the airport roundabout and to the PY03: relevant for anyone who travels often or rents to people who do.
Luque's other public work, on the Paso Carreta stream, is described in the guide on flood works in Luque. The full purchase process is in the Primeproperties.com buying guide, and the Real estate service of Partners.com S.A. follows the checks on a property before the deed.