Buying in Coronel Oviedo: 7.5 km urban corridor now 80% complete

Park path at night lit by street lamps, with benches and flower beds

The Ministry of Public Works puts the rebuilding of the old PY02 road through Coronel Oviedo at 80%, with 300 LED lamps installed along a 155,000 m² linear park. Service roads on both sides opened on 19 September; the contract was awarded for 78,790 million guaraníes.

By · Updated

Share
  • LinkedIn
  • WhatsApp
  • Telegram
  • Facebook
  • X

Coronel Oviedo, capital of the Caaguazú department and 132 km from Asunción, is rebuilding the stretch of the old PY02 road that crosses the city. The Ministerio de Obras Públicas y Comunicaciones (MOPC) reported on 3 November 2026 that the Travesía Urbana is 80% complete and entering its final stage. For anyone buying or owning a home along the corridor, this is what is being built and what is already open.

1. The project in figures

  • Length: 7.5 km of the old road, from the western roundabout to the roundabout at km 135.8.
  • Contract: awarded by MOPC Resolution No. 1,599/24 for 78,790 million guaraníes (September 2024).
  • Linear park: 155,000 m² between the two service roads.
  • Progress: above 70% in September 2026; 80% on 3 November.

2. The four parts of the corridor

  1. North and South service roads (colectoras): parallel roads for local traffic, opened on Saturday 19 September 2026 after the closure of the old PY02, known locally as Tape Tuja.
  2. Main axis (eje troncal): designed for the heaviest traffic, with a dual carriageway and new asphalt between the Teletón and Lactolanda roundabouts.
  3. Maristas sector: improved access to schools and service areas.
  4. Linear park: walking areas, a central promenade with a cycle lane, granite-tile pavements and paver-block parking.

3. What is happening now

  • Lighting: 300 LED lamps have been installed with underground cabling; on 3 November the ministry said the 150 double-arm lamps would be switched on the following week.
  • The park: landscaping, preparation of the areas for exercise equipment and a children's playground, and pavements around the park.
  • After the roads: in August the MOPC listed the finishing works that remain once the road part is done: planters, gardening, recreation areas, street furniture, paint and signage.

The 2024 contract also includes storm drainage, lined ditches, deep drainage and improved junctions, plus public spaces such as event areas, toilets, a first-aid unit and a security booth.

What it means if you are buying

  • Check which road the property faces. A home on a service road now has local-traffic access; one on the main axis faces the through traffic.
  • See it at night. With the new lighting being switched on in stages, an evening visit shows what the street looks like after dark.
  • Expect finishing works. At 80%, the park and the finishes are still in progress.
  • Check the property as usual. Public works do not replace the registry and tax checks in the guides on certificates before the deed and on how property tax is calculated.

The whole purchase, with the taxes on the sale, is described in the Primeproperties.com buying guide. The Real estate service of Partners.com S.A. follows the checks before the deed.

Sources

Ask the team

A few lines are enough. The team of Partners.com S.A. in Asunción reads every request and replies in your language.

We send a confirmation link to this address: your request reaches the team only after you confirm it.

Phone (optional)

Country code: type the number (with or without +) or the country name, then pick it from the list.

Digits only, without the country code.