The Ministry of Public Works is paving more than 51 km of streets in Capiatá under Lot 3 of Plan Central 2, an investment of 79,000 million guaraníes with an 18-month contract. On 17 November 2026 the crews were finishing the asphalt on Don Raimundo Montiel street, with work continuing in the town centre and the north.
By Emilio Marruso · Updated
Capiatá, in the Central department, is getting paved neighbourhood streets: the Ministerio de Obras Públicas y Comunicaciones (MOPC) is investing 79,000 million guaraníes there under Lot 3 of Plan Central 2, with an 18-month contract. On 17 November 2026 the ministry reported that crews were finishing the asphalt on Don Raimundo Montiel street, in the Cuarta compañía, while works continue in the town centre and in parts of the first and second compañías, in the north of the municipality.
Key points:
- Lot 3 of Plan Central 2: 79,000 million guaraníes and an 18-month contract for Capiatá alone.
- More than 51 km of streets in the town, with physical progress at 56% on 2 October 2026.
- 13 streets named by the ministry already had their asphalt finished or the works concluded in August.
1. The project in figures
- Length in Capiatá: more than 51 km of roads in Lot 3, according to the MOPC note of 2 October 2026.
- Investment and term: 79,000 million guaraníes, with a contract term of 18 months; the lot was awarded to the company MM S.A.
- Progress: 56% of physical execution on 2 October 2026; the November note gives no new percentage.
- The whole plan: six towns of the Central department (Areguá, Capiatá, Guarambaré, Itá, Ñemby and San Lorenzo) and an estimated reach of 833,471 inhabitants.
2. The streets named by the ministry
In August 2026 the MOPC listed the sections already finished. Our arrangement of the three notes by stage:
- Asphalt complete (August): San Roque–Cerrito, Medalla Milagrosa, Petirosy, Parque del Sol, Ángel Riquelme and San Juan–Santa Rita.
- Works concluded (August): Compañía 17 Cerrito, Humaitá–Compañía 17, Santo Domingo Savio, San Roque González de Santacruz with Gobernador Irala, Gobernador Irala, Padre Fidel Maíz and RI 6 Boquerón.
- Second asphalt layer under way (August): Juan Ángel Ayala.
- Asphalt being finished (November): Don Raimundo Montiel, in the Cuarta compañía.
- Still in progress (November): the town centre and sectors of the first and second compañías, in the north.
In August the ministry also noted that many sections already paved along their whole length were waiting only for road markings and other finishing work before final opening.
3. What is built on each street
- Surface: levelling and a layer of asphalt concrete.
- Storm drainage: culverts, kerbs with gutters, dips and deep drains.
- Road safety: signs and safety elements.
- At the door: adapted access to homes and replacement of drinking-water pipes.
4. Capiatá and Areguá side by side
Areguá, the neighbouring lot of the same plan, has 38.25 km of streets and 56,815 million guaraníes, as described in the guide to paving in Areguá. By our arithmetic, Capiatá's lot is 22,185 million guaraníes larger, 39% more, for a network of streets at least a third longer.
What it means if you are buying
- Find the street on the list. The ministry names 15 streets out of more than 51 km: for a property elsewhere, ask the municipality or the MOPC whether its street is included before counting on new paving.
- Check the water connection. The works replace drinking-water pipes: ask whether the house's connection has already been redone or is still to come.
- Expect works at the door. In the centre and the north works are still under way; finished sections may still lack markings.
- Check the property as usual. Public works do not replace the registry and tax checks described in the guides on certificates before the deed and on how property tax is calculated.
The whole purchase, with the taxes on the sale, is described in the Primeproperties.com buying guide. The Real estate service of Partners.com S.A. follows the checks before the deed.