Caacupé is about to get a sewer network with its own treatment plant: 40 km of collector sewers, which the Ministry of Public Works expects to finish within two to three months of 13 November 2026. A first plan of household connections covers between 2,500 and 3,000 homes, while the 16 km road to Piribebuy, worth ₲19,692 million, was 24.38% complete.

By · Updated

Share
  • LinkedIn
  • WhatsApp
  • Telegram
  • Facebook
  • X

Caacupé, in the Cordillera department, will have a sewer network with its own wastewater treatment plant: 40 km of collector sewers and 7 km of pumping mains. On 13 November 2026 the Ministerio de Obras Públicas y Comunicaciones (MOPC) reported that the minister expects the works to be finished «in the next two to three months»; a first plan of household connections is projected at between 2,500 and 3,000 homes.

Key points:

  • Sewers: 40 km of collectors, 7 km of pumping mains and a plant with lagoons and artificial wetlands; more than 20,000 people will benefit, according to the MOPC.
  • Connections: an initial projection of 2,500 to 3,000 homes, to be extended progressively.
  • Road: 16 km of asphalt between Caacupé and Piribebuy, ₲19,692,361,855, a 15-month contract, 24.38% physical progress on 13 November.

1. The sewer network in figures

  • Collectors: 40 km of sewer collectors and 7 km of pumping mains carrying wastewater to the treatment complex.
  • Treatment plant: two facultative lagoons of three hectares each and a maturation lagoon, followed by one hectare of artificial wetlands spread over seven ponds, before discharge into the receiving stream.
  • Equipment: pumps and electricity generators; the minister's visit took place at Pumping Station No. 1, where pending works were checked.
  • Timing: «in the next two to three months», in the minister's words of 13 November 2026.
  • Homes: a future household-connection plan with an initial projection of 2,500 to 3,000 homes, to be widened progressively to different sectors of the town.

2. The road to Piribebuy

On the same day the MOPC inspected the paving of the 16 km linking Caacupé and Piribebuy:

  1. Contract: ₲19,692,361,855 funded by the MOPC, awarded to Iniciativas Constructivas S.A. (ICSA), 15 months in total: three for the basic design and twelve for the works.
  2. Progress: 24.38% on 13 November 2026.
  3. Works under way: clearing of the right of way and patching of the existing cobblestones; asphalt-concrete levelling on 3,890 metres and a 5 cm asphalt layer on another 3,707 metres.
  4. Drainage: a 0.80 m pipe culvert and concrete kerbs, with 160 metres of kerb and gutter already built.
  5. At the door: adapted access to homes and replacement of drinking-water pipes along the route.

3. Our figures

  • Cost per kilometre of the road: ₲19,692,361,855 over 16 km gives ₲1,230.77 million per km (our division).
  • Finish window for the sewers: two to three months from 13 November 2026 means between 13 January and 13 February 2027, if the minister's forecast holds.
  • Who is connected first: the first plan covers 2,500 to 3,000 homes, while the MOPC speaks of more than 20,000 people benefiting overall. Not every house on the network will be connected in the first stage.

What it means if you are buying

  • Ask whether the street has a collector. The network is 40 km long: check with the municipality or the MOPC whether the property's street is on it, and whether it is in the first connection plan.
  • Do not price the connection in yet. The network is not in service and household connections come after: until then the house works with its current system.
  • Check the water connection on the Piribebuy road. The paving replaces drinking-water pipes along the route: ask whether the house's connection has already been redone.
  • Check the property as usual. Public works do not replace the registry and tax checks described in the guides on certificates before the deed and on how property tax is calculated.

The whole purchase, with the taxes on the sale, is described in the Primeproperties.com buying guide. The Real estate service of Partners.com S.A. follows the checks before the deed.

Sources

Ask the team

A few lines are enough. The team of Partners.com S.A. in Asunción reads every request and replies in your language.

We send a confirmation link to this address: your request reaches the team only after you confirm it.

Phone (optional)

Country code: type the number (with or without +) or the country name, then pick it from the list.

Digits only, without the country code.

At least 20 words: what you are looking for, budget range if relevant, and your timeline. No links, please.

Your request goes to Partners.com S.A., the company that provides the services of Prime Properties.

All guides and news