Asunción is building storm drains in three river basins: Santo Domingo, which serves Manorá, Las Lomas and Santo Domingo, is 36% complete. In San Pablo the Itay works are at 61% and the Lambaré works at 50%.
By Emilio Marruso · Updated
Heavy rain and flooded streets are a practical question for anyone who buys or owns a home in Asunción. The Municipalidad de Asunción is building storm drains in three river basins of the city, and on 28 October 2026 it reported 51 blocks finished and open to traffic. The figures below come from the municipality's progress reports of 21 October and 28 October, basin by basin.
1. Santo Domingo basin: Manorá, Las Lomas and Santo Domingo
This system drains towards the Mburicaó stream through the Santo Domingo stream.
- Planned: 3,017 metres of culverts and 20,547 m² of concrete paving.
- Built: 610 metres of culverts and 3,480 m² of paving; physical progress 36%.
- Reopened streets: three blocks of Dr. Maciel, one of Nuestra Señora del Carmen, two of Presbítero Justo Román and two of Augusto Roa Bastos.
- Latest work: culverts on Melvin Jones and Roque Centurión Miranda, excavation on Presbítero Justo Román, paving and kerbs on Soldado Desconocido.
2. Itay basin: San Pablo, around the Mercado de Abasto
- Planned: 4,074 metres of culverts and 35,400 m² of paving.
- Built: 2,386 metres of culverts and 19,946 m² of paving; progress 61%, 26 blocks finished and open.
- Reopened streets include: Epifanio Méndez Fleitas, Yerutí, Aztecas and Von Sastrow.
3. Lambaré basin: San Pablo
- Planned: 3,033 metres of culverts and 30,456 m² of paving.
- Built: 1,302 metres of culverts and 8,526 m² of paving; progress 50%, 15 blocks finished and open.
- Reopened streets include: Yporá, Guatambú and Incienso.
4. No completion date
The reports give no end date for any of the three basins. The municipality says the works advance with adjustments for each area, in some cases through amended contracts, and that persistent rain causes further delays, because excavation can only resume once the ground has drained and is safe.
What it means if you are buying or own a home
- Check the street, not just the neighbourhood. The reports list the blocks already reopened; a home on a street still under works may face closures for some time.
- Manorá and Las Lomas are at the earliest stage. With 36% progress, most of the Santo Domingo system is still to be built.
- Works mean disruption first, drainage later. Excavation and paving close streets before the new culverts start to work.
- Follow the progress reports. The municipality publishes them on its website, with the streets worked on each week.
The whole purchase is described in the Primeproperties.com buying guide. The Real estate service of Partners.com S.A. follows the checks before the deed.