# Buying a home in Areguá: paving of 38.25 km past 55% complete

The Ministry of Public Works is improving 38.25 km of streets in Areguá under Lot 2 of Plan Central 2, an investment of 56,815 million guaraníes. On 8 November 2026 the ministry put physical progress above 55%, with road markings already painted on Bicentenario and Yukyty–Caacupemí streets.

By [Emilio Marruso](https://primeproperties.com/author/emilio-marruso) · Updated 22 November 2026

Share
-
-
-
-
-

Areguá, on the shore of Lake Ypacaraí in the Central department, is one of the towns where the Ministerio de Obras Públicas y Comunicaciones (MOPC) is paving neighbourhood streets under **Plan Central 2**. On Sunday 8 November 2026 the new Minister of Public Works, Juan Carlos Baruja, chose Areguá for his [first site visit](https://mopc.gov.py/primer-recorrido-ministro-de-obras-verifica-trabajos-en-central/), and the ministry reported that physical progress on the works has passed 55%. Anyone buying or owning a home in the town can check whether their street is on the list and what is being built.




## 1. The project in figures




- **Length in Areguá:** 38.25 km of streets, all in Lot 2 of Plan Central 2.

- **Investment:** 56,815 million guaraníes for Lot 2, according to the [MOPC note of 14 August 2026](https://mopc.gov.py/ministra-centurion-verifica-obras-del-plan-central-en-aregua-y-luque/).

- **The whole plan:** more than 134 km of roads in five lots, with works in Areguá, Capiatá, Guarambaré, Itá, Ñemby and San Lorenzo.

- **Progress:** 54.6% of physical execution on [30 September 2026](https://mopc.gov.py/plan-central-2-en-aregua-supera-54-de-avance-en-las-obras-de-mejoramiento-de-tramos-viales/); above 55% on 8 November.

- **Supervision:** the MOPC's Dirección de Caminos Vecinales.




## 2. The 12 streets named by the ministry


The MOPC lists these streets among those being worked on, "in addition to other sectors" of the project:




- Bicentenario, Villarrica, Feliciano Báez and Las Residentas;

- María Auxiliadora–Caacupemí, Pedro Estepa, Villa Amparo and Yukyty–Caacupemí;

- Fray Luis de Bolaños, Cocué Guazú, Capitán Hermosilla and Pedro Juan Fleitas.


On 8 November horizontal road markings had already been painted on two sections: **R8**, on Yukyty–Caacupemí street, and **R1**, on Bicentenario street. In August the ministry described the same pattern: asphalt being laid on some streets, earthworks still under way on others, and markings where paving was finished.




## 3. What is built on each street




- **Sub-base** of hydraulic macadam and a stabilised granular base.

- **Levelling** of the ground.

- **Surface** of asphalt concrete.

- **Storm drainage:** kerbs with gutters, lined ditches and dips that channel rainwater and protect the new road.


The ministry states that the works should improve links between neighbourhoods and access to commercial, farming and tourist areas, including during large events such as the town's traditional Expo Frutilla.




## 4. A second project nearby


Areguá also appears in the [Red Vial Estructurante](https://mopc.gov.py/red-vial-estructurante-pena-y-centurion-supervisan-obras-que-agilizaran-la-movilidad-en-asuncion-luque-ypacarai-patino-aregua-y-san-bernardino/), a public-private partnership of 67.40 km of works that includes the Luque viaduct and a corridor from km 41 of route PY02 linking Ypacaraí, Patiño, Areguá and Luque. Its timetable runs to April 2028.




## What it means if you are buying




- **Find the street on the list.** The ministry names 12 streets plus "other sectors": if the property is on a street not named, ask the municipality or the MOPC whether it is included before counting on new paving.

- **See the street in the rain.** Drainage is part of the works: until a section is finished, a rainy-day visit shows how water runs off.

- **Expect works at the door.** With progress just above half, many streets are still at the earthworks or base stage.

- **Check the property as usual.** Public works do not replace the registry and tax checks described in the guides on [certificates before the deed](https://primeproperties.com/real-estate/paraguay-property-deed-certificates-before-signing) and on [how property tax is calculated](https://primeproperties.com/real-estate/paraguay-property-tax-how-it-is-calculated).


The whole purchase, with the taxes on the sale, is described in the [Primeproperties.com buying guide](https://primeproperties.com/buying-in-paraguay). The [Real estate service](https://partners.com/en/paraguay/services/real-estate) of Partners.com S.A. follows the checks before the deed.




## Sources




- [MOPC — First visit: the Minister of Public Works checks works in Central (8 November 2026)](https://mopc.gov.py/primer-recorrido-ministro-de-obras-verifica-trabajos-en-central/)

- [MOPC — Plan Central 2 in Areguá passes 54% progress (30 September 2026)](https://mopc.gov.py/plan-central-2-en-aregua-supera-54-de-avance-en-las-obras-de-mejoramiento-de-tramos-viales/)

- [MOPC — Minister checks Plan Central works in Areguá and Luque (14 August 2026)](https://mopc.gov.py/ministra-centurion-verifica-obras-del-plan-central-en-aregua-y-luque/)

- [MOPC — Red Vial Estructurante: works for Asunción, Luque, Ypacaraí, Patiño, Areguá and San Bernardino (24 October 2026)](https://mopc.gov.py/red-vial-estructurante-pena-y-centurion-supervisan-obras-que-agilizaran-la-movilidad-en-asuncion-luque-ypacarai-patino-aregua-y-san-bernardino/)

⭐ Follow Prime Properties on Google

Want to find our property guides and news more easily? Add primeproperties.com to your preferred sources in Google Search.

[Add primeproperties.com to your preferred sources →](https://www.google.com/preferences/source?q=primeproperties.com)

Contact form: https://primeproperties.com/contact

[All guides and news](https://primeproperties.com/real-estate)